Numbers: Omitting date from time for duration calculation
Hi all,
i am currently using Numbers to track some stats and information for my job. i have a table that ive created to show an event's scheduled Start and End Time. and when i have the actual Start and End time of that particular event, i would like to show the difference in duration between scheduled and actual.
however, the scheduled time that i have inserted is tied to a date. (Eg: keyed in the scheduled time on Monday.) so when the event starts, which is a few days later, and when i enter the Actual timings and do the difference in duration, the scheduled time remains tied to Monday which will return a durations in days instead of just comparing the time difference.